| Unincorporated Miami-Dade County (RER — Kendall, West Kendall, Westchester, The Hammocks, Tamiami, Country Walk) | 25 calendar days (~18 bus. days) | 12–48 calendar days | $133.38 flat (exact window/door change-out, + $25.65 CPBC up-front fee) or $150.82 flat (residential retrofit) + $0.60/$1k County Code & 2.5% FL surcharges (IO 4-63 · included in our price) | Miami-Dade RER Online Portal · HVHZ (175 mph) |
|---|
| Unincorporated Palm Beach County (PZB — West Boca, West Delray, West Boynton, Lake Worth Corridor, The Acreage) | 26 calendar days (~19 bus. days) | 14–45 calendar days | $75.00 first $2,000 of job value + 2.50% ($2,001–$10k) + 1.75% ($10,001–$100k) + $5 Lien Law fee & 2.5% FL surcharges ($4 min · Ord. 2009-038 · included in our price) | Palm Beach County ePZB Portal · FBC 170 mph |
|---|
| Unincorporated Broward County (BMSD — Broward Municipal Services District) | 27 calendar days (~19 bus. days) | 14–49 calendar days | 3.00% of job value ($125.00 min base fee) + $0.52/$1k BORA surcharge & 2.5% FL surcharges (Broward Admin Code § 40.29 · included in our price) | Broward BCS ePermits · HVHZ (170–180 mph) |
|---|
| Unincorporated Martin County (Building Dept. — Palm City, Jensen Beach, Hobe Sound, Port Salerno, Rio) | 21 calendar days (~15 bus. days) | 10–38 calendar days | $75.00 permit fee (up to $25k job value; $100 for $25k–$50k) + $25.00 plan review (up to $25k; $100 for $25k–$50k) + $75.00 per inspection & 2.5% FL surcharges ($4 min · Eff. 7/1/2026 Schedule · included in our price) | Martin County Accela Citizen Access · FBC 154–165 mph |
|---|
| Unincorporated St. Lucie County (Building & Code Regulation — Hutchinson Island, Lakewood Park, Indian River Estates) | 20 calendar days (~14 bus. days) | 10–35 calendar days | $100.00 flat (Residential Doors & Windows / Overhead Garage Doors; $100 Storm Shutters) + $5.00 automated permit fee & 2.5% FL surcharges ($4 min; $109.00 total · Eff. 7/7/2026 Schedule Ex. A · included in our price) | St. Lucie County EnerGov CSS · FBC 150–160 mph |
|---|
| Davie (Broward) | 16 calendar days (~11 bus. days) | 7–22 calendar days | 0.95% of job value ($55 min) + 0.75% plan review ($25 min; 1.70% combined) + 6% tech fee, $0.52/$1k BORA & 2.5% FL surcharges (Davie Fee Schedule · included in our price) | Town of Davie ePermits · HVHZ (170–180 mph) |
|---|
| Pompano Beach (Broward) | 18 calendar days (~13 bus. days) | 6–27 calendar days | 2.75% of project value up to $250k ($65.00 min) + $5 C of C, 2% tech fee, $0.52/$1k BORA & 2.5% FL surcharges (Oct 2026 Fee Schedule · included in our price) | Pompano ePlan · HVHZ (170–180 mph) |
|---|
| Port St. Lucie (St. Lucie) | 19 calendar days (~14 bus. days) | 8–34 calendar days | $75.00 first window/exterior door + $5.00 each additional opening (or $150.00 flat residential alteration) + $5 NOC fee & 2.5% FL surcharges ($4 min · Code § 150.001 / Ord. 22-67 · included in our price) | PSL Contractor E-Permits Portal · FBC 159–160 mph |
|---|
| Stuart (Martin) | 23 calendar days (~16 bus. days) | 12–40 calendar days | $150.00 up to $5k job value ($575 for $5,001–$10k; $650 for $10,001–$100k) + 0.30% residential plan review ($75.00 min) & 2.5% FL surcharges (Code App. A Ch. 10 / Res. 62-2026 · included in our price) | City of Stuart OpenGov Portal · FBC 160 mph |
|---|
| Tamarac (Broward) | 24 calendar days (~17 bus. days) | 10–66 calendar days | $141.00 first 5 windows/doors/shutters + $23.00 each additional opening ($273 garage door) + $0.30/$1k training, $0.52/$1k BORA & 2.5% FL surcharges (Res. R-2021-137 · included in our price) | Tamarac ePermits (BP26-) · HVHZ |
|---|
| Fort Pierce (St. Lucie) | 24 calendar days (~17 bus. days) | 12–42 calendar days | 0.50% of valuation for residential construction ($100.00 min; or 1.25% all other construction, $100.00 min) + 0.25% plan review ($75.00 min) & 2.5% FL surcharges (Eff. 7/8/2025 Schedule · included in our price) | Fort Pierce EPL Portal · FBC 150–160 mph |
|---|
| Miami (Miami-Dade) | 28 calendar days (~20 bus. days) | 9–61 calendar days | 0.50% of construction cost for 1–3 family remodeling ($110.00 min; $45 under $2,500; 50% SAVE reduction eligible under Sec. 10-20) + County/FL surcharges (Res. R-26-0200 · included in our price) | Miami iBuild / ePlan (BD26-) · HVHZ (175 mph) |
|---|
| Wellington (Palm Beach) | 28 calendar days (~20 bus. days) | 22–62 calendar days | $150.00 min (up to $7,500 value) + 2.00% of value ($7,500.01–$100k) + 1.75% ($100k–$500k) + 2.5% FL surcharges (Wellington Fee Schedule · included in our price) | Village of Wellington (BP26-) · FBC 170 mph |
|---|
| Boynton Beach (Palm Beach) | 29 calendar days (~21 bus. days) | 9–75 calendar days | 2.30% of construction value up to $1M ($80.00 min; 1.0% plan review deposit credited at issuance) + 0.05% Green Bldg & 2.5% FL surcharges (Boynton Schedule · included in our price) | SagesGov (B-2026- / PR-) · FBC 170 mph |
|---|
| Hollywood (Broward) | 29 calendar days (~21 bus. days) | 13–65 calendar days | $100.00 first $1,000 of job value (10% min) + 2.20% of value ($1,001–$1M) + C of C (3% of permit fee, $45 min), $0.52/$1k BORA & 2.5% FL surcharges (Hollywood Schedule · included in our price) | Hollywood Citizen Access (STRUC-WDS-) · HVHZ |
|---|
| Greenacres (Palm Beach) | 31 calendar days (~22 bus. days) | 8–67 calendar days | 2.50% of construction value up to $100k ($75.00 min; 2.00% from $100k–$300k) + 2.5% FL surcharges ($4 min · Greenacres Building Division Schedule · included in our price) | Greenacres Building Dept (B-2026-) · FBC 170 mph |
|---|
| Palm Beach Gardens (Palm Beach) | 32 calendar days (~23 bus. days) | 15–53 calendar days | 1.80% of job value up to $100k ($18/$1,000; $75.00 min) + 10% plan review surcharge, 1% training & 2.5% FL surcharges (FY 2026–27 Master Schedule · included in our price) | PBG GeoCivix Portal (RRENO-) · FBC 170 mph |
|---|
| Coral Springs (Broward) | 33 calendar days (~24 bus. days) | 9–86 calendar days | $142.00 base + $23.00 per window/door unit ($153 for 1–3 shutters + $39 each add'l) + $0.63/$1k edu/tech, $0.52/$1k BORA & 2.5% FL surcharges (Item 20 Schedule · included in our price) | Coral Springs ePermits (EBP26-) · HVHZ |
|---|
| Plantation (Broward) | 36 calendar days (~26 bus. days) | 15–48 calendar days | 1.75% of job value ($95.00 min for window, door & shutter permits) + 3.5% admin surcharge, $0.25/$1k cert, $0.52/$1k BORA & 2.5% FL surcharges (Code Table 5-1 · included in our price) | Plantation Citizen Access (B26-) · HVHZ |
|---|
| Jupiter (Palm Beach) | 37 calendar days (~26 bus. days) | 17–52 calendar days | 2.00% of value of work performed ($75.00 min; 30% due at application submittal) + 2.5% FL surcharges ($4 min · Code Sec. 21-55 / Ord. 24-07 · included in our price) | Jupiter JCDS Portal (BLDR) · FBC 170 mph |
|---|
| Deerfield Beach (Broward) | 37 calendar days (~26 bus. days) | 14–45 calendar days | $75.00 flat up to $5,000 construction cost; 2.50% of cost from $5,001 to $2M + $75 C of C, $0.52/$1k BORA & 2.5% FL surcharges (Res. 2024/202 · included in our price) | Deerfield EnerGov (DFB2026-B) · HVHZ |
|---|
| Delray Beach (Palm Beach) | 38 calendar days (~27 bus. days) | 21–52 calendar days | $50.00 first $1,000 of job value + $42.00 per add'l $1,000 (4.20% residential alteration rate; 50% plan check credited) + 2.5% FL surcharges (Res. 208-24 · included in our price) | Delray eServices (BLDR-) · FBC 170 mph |
|---|
| Miramar (Broward) | 38 calendar days (~27 bus. days) | 25–109 calendar days | 1.75% of construction value + $75.00 residential application fee (+ 0.75% plan review & 8% admin surcharge) + $0.52/$1k BORA & 2.5% FL surcharges (FY 2026 Schedule · included in our price) | Miramar EnerGov (BLDR-) · HVHZ |
|---|
| Weston (Broward) | 38 calendar days (~27 bus. days) | 13–62 calendar days | $121.67 base (first $1,000) + $15.50 per add'l $1,000 (1.55% up to $1.25M) + $200 tech/admin fee, 0.03% edu, $0.52/$1k BORA & 2.5% FL surcharges (Res. 2026-133 · included in our price) | Weston CAP Online Permit Application · HVHZ |
|---|
| West Palm Beach (Palm Beach) | 41 calendar days (~29 bus. days) | 21–79 calendar days | $105.00 min (up to $1,000 value); $130.00 (up to $2,500) + 2.50% over $2,000 ($580 combined plan review & permit fee at $20k value) + 2.5% FL surcharges (Res. 188-24 · included in our price) | WPB ePermits (RES-BLDG) · FBC 170 mph |
|---|
| Sunrise (Broward) | 41 calendar days (~29 bus. days) | 18–53 calendar days | $248.11 first 3 window/door openings + $17.11 each additional opening ($222.44 general permit min) + $0.52/$1k BORA & 2.5% FL surcharges (Sunrise Building Schedule · included in our price) | Sunrise Community Development · HVHZ |
|---|
| Boca Raton (Palm Beach) | 42 calendar days (~30 bus. days) | 21–78 calendar days | $100.00 min (first $500 of contract value) + 1.60% of construction value over $500 (includes plan check) + 2.5% FL surcharges ($4 min · Sec. C(2) · included in our price) | Boca ePlans (B-2026- / BPM-) · FBC 170 mph |
|---|
| Fort Lauderdale (Broward) | 43 calendar days (~31 bus. days) | 14–76 calendar days | 1.75% of construction cost ($131.00 minimum) + $5 lien fee, $0.52/$1k BORA surcharge & 2.5% FL surcharges (Code Sec. 9-48 · included in our price) | LauderBuild (BLD-WIN / BLD-WIN-WT) · HVHZ |
|---|
| Pembroke Pines (Broward) | 47 calendar days (~34 bus. days) | 20–78 calendar days | $124.42 first window/door opening + $13.84 each additional opening (Sec. 150.16 III.A; or 3.79% over $2,500 for structural alterations) + $0.52/$1k BORA & 2.5% FL surcharges (included in our price) | Pembroke Pines Building Dept (RO26-) · HVHZ |
|---|
| Lake Worth Beach (Palm Beach) | 47 calendar days (~34 bus. days) | 20–133 calendar days | 3.00% of construction value up to $500k ($135.00 min up to $3,000; 50% plan filing deposit at submittal) + 2.5% FL surcharges (FY 2027 Schedule · included in our price) | Click2Gov + Historic COA review · FBC 170 mph |
|---|