How Long Do Impact Windows Take From Contract to Final Inspection in South Florida? (2026 Lead Times)
A complete impact window and door replacement project in South Florida typically takes 8 to 12 weeks from contract signing to installation, followed by 1 to 5 days of on-site installation and final municipal building inspection. Based on 103 completed 2026 factory orders tracked by Republic’s project management desk (Omar Tellez and Camila Diaz) and October 2026 manufacturer schedules, current factory production lead times from order placement to warehouse delivery run 4 to 6 weeks for ECO Window Systems (2026 median: 4.7 weeks), 6 to 8 weeks for CWS / Custom Window Systems (2026 median: 7.9 weeks; recent fall orders arriving in 6.1–6.4 weeks), 6 to 9 weeks for ES Windows (2026 median: 8.4 weeks; late-October 2026 factory ETA: 6–7 weeks), and 8 to 11 weeks for PGT WinGuard (2026 tracked custom order: 10.8 weeks).
- 8–12 WeeksTypical total timeline from contract signing to installation in South Florida
- 4.7 WeeksECO Window Systems 2026 median factory delivery (n = 34 completed orders)
- 6–8 WeeksCurrent Oct 2026 factory ETA for CWS (6–8 wks) & ES Windows (6–7 wks)
- 1–5 DaysTypical on-site installation time by Republic’s dedicated installation crews
· Written by Ashley Rivera · Verified against Republic Windows, Doors & Roofing internal operations logs (Florida Certified General Contractor CGC1533058 · Roofing Contractor CCC1337395).