10% Deposit → Materials Order26 DaysAhead of 30d target
Materials Order → Delivered15 Days14d Factory + 1d QC
Delivered → Install Scheduled1.8 DaysDirect handoff, 0d pending hold
Payment Milestones10% Paid ($3,480) · 40% Paid ($13,920) · 50% Due at Install
#all-project-updates
CM
Carlos MendezFIELD CREW Lead Field Superintendent · Sep 16, 2026 · 2:42 PM EDT
Stage 2 · Measurements (2d)
Laser measurements are 100% complete for all 18 windows and 3 impact doors at 2840 NE 26th St. Every rough opening is clean concrete block (CMU) with existing wood bucks in great condition. Uploaded the 21-opening schedule to Engineering.
Ashley RiveraREPUBLIC TEAM Permitting & Project Coordinator · Oct 09, 2026 · 3:48 PM EDT
Stage 5 · Building Permit (11d)
Great news @Michael & Elena Vance! Following your HOA approval on Sep 28, the City of Fort Lauderdale Building Department just approved and issued Building Permit #BP-26-04912 across both Structural and Zoning reviews. Once your 40% milestone payment is completed, our Purchasing Desk will release your materials order to the factory immediately.
Michael VanceHOMEOWNER Oct 10, 2026 · 10:19 AM EDT Awesome! Just submitted the 40% milestone payment online. Thank you for pushing the permit through so fast!
AR
Ashley RiveraREPUBLIC TEAM Oct 10, 2026 · 1:56 PM EDT Received and confirmed! Your Materials Order (#PO-88419 & #PO-88420) has been released to production today—total time from 10% deposit to Materials Order was just 26 days!
RT
Republic Stage TrackerSTAGE LOG BOT Automated Factory & Warehouse EDI · Oct 25, 2026 · 3:10 PM EDT
Stage 9 · Delivered (QC Passed)
STAGE TRANSITION LOG: Order #RW-2026-4182 completed Stage 8 (In Production) in 14 days and has been DELIVERED to Republic's Fort Lauderdale Warehouse (2901 SW 3rd Ave, STE 1B). All 18 PGT WinGuard® Aluminum windows and 3 ECO Commercial impact doors passed our 21-point glass, frame finish, and hardware inspection.
Ashley RiveraREPUBLIC TEAM Permitting & Project Coordinator · Oct 27, 2026 · 10:15 AM EDT
Stage 10 · Installation Scheduled
Your project is now in Stage 10: INSTALLATION SCHEDULED! Since your materials passed warehouse QC on Saturday, we moved straight from Delivered to Installation Scheduled—your 3-day installation with Carlos Mendez and Crew #2 is locked in for Tuesday, Nov 3 through Thursday, Nov 5 (8:00 AM arrival). Feel free to drop any questions or comments right below!
Elena VanceHOMEOWNER Oct 27, 2026 · 11:04 AM EDT We're so excited! Should we move the patio sectional on the covered lanai before Tuesday morning, or will the crew help slide it back?
CM
Carlos MendezFIELD CREW Oct 27, 2026 · 11:18 AM EDT Hi Elena! Don't worry about lifting heavy furniture—our crew will move the lanai sectional and cover everything with heavy drop cloths and plastic zip-walls on Tuesday morning.
Stage Breakdown & Audit Logs
1. 10% DepositSep 14
Entered: Sep 14, 2026 · 10:15 AM EDT · Completed: Sep 14, 2026 · 11:02 AM EDT
1d in stage vs 1d SLA · Ahead of SLA · Owner: Ashley Rivera